Al-Dhamar Primary School – Site Plan
Key Strategies for 1-Month Completion
– Use Prefabricated Materials
– Parallel Task Execution
– Local Workforce Mobilization
– Simplified Design
Day-by-Day Construction Plan
– Days 1-2: Site Preparation
– Days 3-7: Foundation and Flooring
– Days 8-15: Wall Construction
– Days 10-20: Roofing Installation
– Days 15-22: MEP Installation
– Days 20-25: Finishing Works
– Days 26-28: Furniture and Setup
– Days 29-30: Inspection and Handover
Budget Breakdown
– Site preparation: $800
– Foundations and flooring: $4,000
– Wall construction: $6,000
– Roofing: $3,000
– Electrical and plumbing: $2,000
– Finishing: $1,500
– Furniture: $2,000
– Miscellaneous: $700
– Total Estimate: $25,000-$30,000
Key Risks and Mitigation
– Delays in material delivery: Source locally.
– Labor shortages: Hire extra workers.
– Budget overruns: 10% contingency fund.
Summary
– Timeline: 30 days.
– Cost: $25,000-$30,000.
– Focus: Speed, affordability, and essential facilities
What We Do
Community Helper School
Education for All
We believe in the power of education to break the cycle of poverty. Our programs focus on providing access to quality education for children from economically disadvantaged backgrounds.
Basic Needs Assistance
We understand the importance of meeting basic needs. Community Helpers School offers support in the form of food, clothing, and shelter to families facing financial hardships.
Skill Development
We empower individuals to become self-sufficient by offering skill development programs. Through vocational training, we aim to enhance employment opportunities and create sustainable livelihoods.
Contributions
Spread the word about our program. Even a small donation will make a huge difference.
Building Hope, One Donation at a Time
Illustrate how each contribution, no matter the size, contributes to building a hopeful future.
OUR GALLERY
See Our Photos